Solar

Solarpark Wyandot Solar

Kapazität:
12 MW
Land:
Vereinigte Staaten von Amerika
Region:
Ohio
Inbetriebnahme:
2010
Module:
159200

juwi developed, designed and built the Wyandot Solar Energy Facility, a 12.0 MWp solar PV facility located in Upper Sandusky, Ohio. In June 2009 juwi’s subsidiary executed a 20-year PPA with AEP Ohio. Construction commenced in the fourth quarter of 2009, and the project achieved commercial operation in May 2010.

  • juwi’s construction group, together with a leading Ohio-based subcontractor, commenced construction in October 2009
  • Includes 159,200 ground-mounted, thin-film solar panels on 77-acre plot of land
  • Commercial operation occurred on May 26, 2010
  • In September 2009, juwi transferred its ownership rights in the project to PSEG Solar Source
  • Energy and REC off-taker is AEP Ohio
  • juwi is currently operating, maintaining and monitoring the project on behalf of PSEG Solar Source

Weitere Themen

Neuste Artikel

Deutschland-Premiere: Erstes Innovationsprojekt „Wind+Speicher“ vor der Umsetzung

juwi errichtet in Brandenburg das bundesweit bislang einzige „Wind+Speicher“-Projekt der… mehr

Windpark Kröppen

mehr

Windpark Schwegenheim II

mehr