Solarpark Wyandot Solar

Kapazität:
12 MW
Land:
220
Region:
Ohio
Inbetriebnahme:
2010
Module:
159200

juwi developed, designed and built the Wyandot Solar Energy Facility, a 12.0 MWp solar PV facility located in Upper Sandusky, Ohio. In June 2009 juwi’s subsidiary executed a 20-year PPA with AEP Ohio. Construction commenced in the fourth quarter of 2009, and the project achieved commercial operation in May 2010.

  • juwi’s construction group, together with a leading Ohio-based subcontractor, commenced construction in October 2009
  • Includes 159,200 ground-mounted, thin-film solar panels on 77-acre plot of land
  • Commercial operation occurred on May 26, 2010
  • In September 2009, juwi transferred its ownership rights in the project to PSEG Solar Source
  • Energy and REC off-taker is AEP Ohio
  • juwi is currently operating, maintaining and monitoring the project on behalf of PSEG Solar Source

Zurück zur Übersicht

Weitere Themen

Neuste Artikel

Baustart am juwi-Windpark Lauda-Heckfeld

Windpark liefert jährlich Ökostrom für mehr als 5.300 Haushalte. mehr

Das Jahrhundertprojekt „Energiewende“ fasziniert noch immer

Als weltweit tätiges Unternehmen der Solar- und Windenergie-Branche bietet juwi viele spannende... mehr

Windenergie: Infotafeln auf dem Höcherberg aufgestellt

Vier beschilderte Stationen vermitteln allerhand Wissenswertes über die Themen Windenergie, Natur,-... mehr